Etango-8 uranium project, Namibia – update

Photo by Bannerman Energy
Name of the Project
Etango-8 uranium project.
Location
Erongo region, about 30 km east-southeast of Swakopmund, in Namibia.
Project Owner/s
Australian- and Namibian-listed uranium development company Bannerman Energy, through its 95%-owned subsidiary Bannerman Mining Resources. The remaining 5% is owned by Namibian charitable body One Economy Foundation.
Project Description
A definitive feasibility study was completed in December 2022. This confirmed to a definitive level the strong technical and economic viability of conventional openpit mining and heap-leach processing of the Etango deposit as an eight-million-tonne-a-year throughput operation – for average output of 3.5-million pounds a year of triuranium octoxide (U3O8).
In March 2024, a scoping study showed the capacity to increase production to 6.7-million pounds a year of U3O8.
Total production is estimated at more than 15 years, with total production estimated at 52.6-million pounds of U3O8.
Two future-phase development options have been proposed:
- an expansion of mine and plant throughput to 16-million tonnes a year – Etango-XP; and
- a life-of-mine extension with mine and plant throughput maintained at eight-million tonnes a year – Etango-XT.
Potential Job Creation
More than 560 contract personnel are actively working on site.
Net Present Value/Internal Rate of Return
The project has an estimated after-tax net present value, at an 8% discount rate, of $390-million and an internal rate of return of 21.1%.
Capital Expenditure
Preproduction capital expenditure is estimated at $353.5-millon.
Planned Start/End Date
A final investment decision (FID) is targeted in 2025.
Latest Developments
Early works are advancing on budget and on schedule. As of March 26, the 24-month bulk earthworks contract was about 66.5% complete, with work centred on the heap-leach pads, ponds and wet plant terraces.
Blasting, crushing and screening of heap-leach drainage aggregate were also progressing to plan, with about 24% of the total material requirement completed.
Concrete works for the primary crusher, stockpile tunnel, fine-ore silo and associated dry plant infrastructure had reached about 32% completion, with 5 509 m³ of concrete poured.
Phase 1 of the permanent water supply pipeline was about 70% complete and ahead of schedule, while a definitive power supply agreement had been signed with NamPower. Design of the acid storage and handling facility at Walvis Bay was about 39% complete.
Detailed engineering also continued to advance. Civil and mechanical design for the dry plant was about 93% complete, with concrete drawings already issued for construction, and structural steel drawings advancing for tender in the second quarter of 2026.
Wet plant engineering was about 23% complete. Current work is focusing on optimisation testwork ahead of Phase 3 concrete construction and later structural, mechanical, piping and platework works.
Bannerman has said the project remains on track for a targeted final investment decision and full-scale construction launch later in 2026.
Key Contracts, Suppliers and Consultants
Wood plc (study lead – process plant design and related infrastructure, plant capital and operating cost estimates); Qubeka Mining Consultants (geology review, mineral reserve estimate, mine planning and mining cost estimates); Snowden Optiro (mineral resource estimate); Creo Engineering Solutions (engineering support for Bannerman owner’s team); MineTechnics (openpit geotechnical parameters); Lund Consulting Engineers (water supply infrastructure); Addiza Energy Solutions (external electrical supply infrastructure); A.Speiser Environmental Consultants (environmental-impact assessments); Namisun Environmental Projects & Developments (conceptual mine closure plan); AN Construction (pumpstation foundations and pipe bridge over the Swakop river); and Tulela Mining & Construction (blasting, crushing and screening of heap leach drainage aggregate).
Contact Details for Project Information
Bannerman Energy, tel +61 8 9381 1436 or email info@bmnenergy.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation















