Bellevue wet paste plant, Australia

Image of Bellevue Mine rockface

Photo by Bellevue Gold

24th April 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Bellevue wet paste plant.

Location
Western Australia.

Project Owner/s
Australia's newest major gold producer Bellevue Gold.

Project Description
Bellevue Gold has approved the construction of a new 120 m3/h wet paste plant. The plant will service the high-grade Deacon and Deacon North mining areas. 

Paste fill involves taking tailings from the processing plant thickener discharge, dewatering them through a filter, mixing them with cement binder and depositing the resulting paste into underground voids. 

The introduction of paste fill is expected to deliver long-term value through improved production consistency and increased safety. 

It will also allow for higher recovery from the Deacon and Deacon North orebodies, with overall recovery expected to increase by about 7%, translating into an additional 100 000 oz mined over the current reserve life. 

The additional material, previously left behind as pillars, is higher-grade ore within these zones. 

The paste fill will provide continuous wall support, assisting in controlling dilution, protecting head grade and sustaining revenue margins. 

It will also reduce seismic risk by eliminating large underground voids and providing early confinement to stope walls, improving workforce safety and enabling more predictable mining conditions. 

About 30% of tailings produced are expected to be deposited underground through paste filling, reducing volumes to the surface tailings storage facility and extending its life. 

While paste fill will slightly extend stope turnover times in the higher-grade areas, owing to curing requirements; this is expected to be offset by the increased tonnes.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
Bellevue approved the A$35-million to A$40-million paste plant, including a 10% contingency on February 17, 2026.

Planned Start/End Date
Construction will start in the 2026 financial year, with completion estimated by in mid-2027, with paste filling to start immediately thereafter.

Latest Developments
Long-lead items, including disc filters, a paste mixer and a cement silo, have been ordered. GR Engineering Services is expected to be appointed to construct the plant. 

Two previously drilled boreholes will be used to deliver paste underground.

Key Contracts, Suppliers and Consultants
GR Engineering Services (wet paste plant construction).

Contact Details for Project Information
Bellevue Gold, tel +61 8 6373 9000 or email admin@bgl.gold.
 

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Projects

Image of Argentina flag and periodic table for copper and gold
Taca Taca copper/gold project, Argentina
Updated 1 hour 16 minutes ago By: Sheila Barradas
Image of Bellevue Mine rockface
Bellevue wet paste plant, Australia
Updated 1 hour 16 minutes ago By: Sheila Barradas

Showroom

Egoli Gas (Pty) Ltd
Egoli Gas (Pty) Ltd

As a reticulator, Egoli Gas provides natural gas to homes and businesses via underground pipes.

VISIT SHOWROOM 
Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.053 0.13s - 104pq - 2rq
Subscribe Now