Azteca processing plant refurbishment reaches 77% completion – Cadence

28th July 2026

By: Creamer Media Reporter

     

Font size: - +

Refurbishment of the Azteca processing plant at London-listed Cadence Minerals' Amapá iron-ore project, in Brazil, has progressed to 77% completion and 43 of the 64 identified work packages now complete.

The company reports that completion of the principal mechanical workstreams has progressively shifted the execution focus to electrical installation, integrated commissioning and operating licence readiness. The feed hopper, transfer conveyor and process tank installation have been completed, while screen refurbishment is substantially complete.

Cadence says management's immediate focus is completing the remaining electrical installations, integrated plant commissioning and completion of the operating licence workstreams.

Subject to successful commissioning and receipt of the operating licence, the company continues to target operational readiness by the end of August.

The Amapá project is an integrated operation comprising mining, rail, port and beneficiation infrastructure. As part of a staged redevelopment strategy for the project, Azteca is planned to be recommissioned as the initial production facility, targeting about 380 000 t/y of about 65% iron concentrate from existing tailings.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Tsurumi Pumps Africa
Tsurumi Pumps Africa

Tsurumi Pumps Africa is a specialist supplier of Japanese-engineered submersible pumping solutions, serving customers across the African continent.

VISIT SHOWROOM 
Essentra Components
Essentra Components

We are responsible manufacturers of essential components. Manufacturing 80 million parts a week, we have over 1 billion parts in stock.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (24/07/2026)
24th July 2026 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.052 0.123s - 116pq - 2rq
Subscribe Now