Uis lithium expansion project, UK – update

Photo by Andrada Mining
Name of the Project
Uis lithium expansion project.
Location
In the Erongo region of Namibia, on mining licence ML134.
Project Owner/s
Critical raw materials producer Andrada Mining, through its subsidiary Uis Tin Mining Company (UTMC).
Project Description
The Uis mine exploits a polymetallic pegmatite-hosted deposit containing tin, tantalum and lithium mineralisation. The mine currently produces tin and tantalum concentrates.
Andrada intends to monetise the lithium contained in the run-of-mine by building a beneficiation circuit that is integrated into the tin and tantalum processing facility of the Uis mine.
The additional integrated circuit will not increase the ore requirements from the mining operation but will rather reprocess the waste material from the tin and tantalum concentrator for lithium enrichment.
Lithium mineralisation predominantly occurs as petalite. During the initial phase, petalite concentrate will be produced for the technical lithium market at an initial target of 50 000 t/y.
Previous feasibility studies towards this initial phase have advanced the project to a prefeasibility level of confidence. Definitive feasibility study (DFS) work is expected during 2026.
Andrada envisages a second phase of development to supply the lithium refining industry with concentrate for producing lithium chemicals for the fast-growing battery industry.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
Not stated.
Capital Expenditure
Not stated.
Planned Start/End Date
The Uis mine lithium expansion project is projected to enter the DFS phase during 2026.
Latest Developments
On February 10, 2026, Andrada announced that UTMC had entered into a cooperation agreement with the European Investment Bank (EIB) to accelerate the feasibility study for the lithium expansion project. Under the agreement, the project will benefit from technical and project development assistance funded by the EU and valued at up to €2-million on a grant basis. The scope of work is intended to advance the project to bankable feasibility level, with a focus on metallurgical testing and related infrastructure studies.
Andrada has also signed a cooperation agreement with the EIB to accelerate the feasibility study for the expansion, with EU-funded technical and project development assistance intended to advance the project to bankable feasibility. The company has said the partnership provides nondilutive support and is aimed at accelerating implementation of the project.
Key Contracts, Suppliers and Consultants
None disclosed.
Contact Details for Project Information
Andrada Mining, tel +27 11 268 6555 or email connect@andradamining.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation
















