Skeena halfway to Eskay Creek completion

Eskay Creek project area

Eskay Creek project area

1st April 2026

By: Marleny Arnoldi

Online News Editor

     

Font size: - +

Since starting development activity on the Eskay Creek gold and silver project in British Columbia in December 2024, precious metals developer Skeena Resources has reached 49% completion of the project, with 66% of project costs having been contractually committed.

As per the company’s updated cost estimate, $659-million is required to bring Eskay Creek into production, of which $354-million remains to be spent.

The cost estimate had to be updated from the prior $560-million envisioned in the 2023 definitive feasibility study owing to general cost escalation as a result of inflationary pressures, optimisation of the permanent camp location and operational design enhancements to improve winter operating conditions.

The company expects initial production from Eskay Creek by the second quarter of 2027 and commercial production during the third quarter of 2027.

CEO and president Randy Reichert says the company’s strategy of initiating development activities well ahead of final permit receipt has delivered meaningful value for shareholders. “By acting early, we reduced project timeline risk and minimised inflationary impacts across key scopes by securing procurement contracts earlier.”

Some of the completed activities on site include receipt of initial large mining equipment, access road bridge replacements, process plant pad mass earthworks and assay lab construction.

The ongoing activities that are progressing on schedule include tailings facility construction, permanent camp construction, water treatment construction, electrical infrastructure construction, process plant construction and process plant detailed engineering.

 

Edited by Marleny Arnoldi
Online News Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

M and J Mining
M and J Mining

M and J Mining are leading suppliers of physical support systems as used by the underground mining industry. Our selection of products are not...

VISIT SHOWROOM 
SAJ Electrics
SAJ Electrics

Smart energy storage solutions for efficient, safe, and profitable power.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.088 0.839s - 107pq - 2rq
Subscribe Now