Sigma cathing up on lost weeks of lithium oxide concentrate production

Lithium ore on conveyor at Grota de Cirilo

Lithium ore on conveyor at Grota de Cirilo

26th October 2026

By: Marleny Arnoldi

Online News Editor

     

Font size: - +

With its Grota de Cirilo complex in Brazil having been under a brief administrative suspension, Canadian miner Sigma Lithium has produced 7 090 t of lithium oxide concentrate between October 5 and 22, and remains on track to scale its production of lithium oxide concentrate to 330 000 t/y by end-2027.

Sigma had postponed its rolling 12-month guidance of 240 000 t by three months while maintaining its 2027 target of 330 000 t of lithium oxide concentrate.

Additionally, the company managed to extend the maturity of a four-year $100-million senior secured debt facility with Synergy Capital by six months from December this year to June 2027.

The extension defers Sigma's repayment by six months, enabling the company to continue ramping up production and building operational cashflow before the new debt maturity date.

Overall, Sigma has repaid more than $90-million of debt since the second quarter of 2024 through cash generation alone. After reducing its total debt by about 40% over the past two years, Sigma had a debt balance of $125-million as of October 21.

For context, Sigma restarted its Grota operation on October 5 after Brazil's Federal Superior Court granted a decision reinstating all of its environmental licences. It stemmed from an emergency motion of suspensive relief owing to the severe economic impact that a prolonged stoppage would cause in the Vale do Jequitinhonha region.

The mine's environmental licences were suspended on September 4 following a civil lawsuit by the Federation of Quilombola Communities of Minas Gerais (N'Golo), which argued the project is located within 2.7 km of the Bau Quilombola traditional territory and under an 8 km consultation threshold.

Sigma will report its third-quarter production and sales results on or about November 13.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

North Ridge Pumps
North Ridge Pumps

North Ridge Pumps is an independent manufacturer of pumps. We have a proven track record for product support and customer service throughout the...

VISIT SHOWROOM 
Egoli Gas (Pty) Ltd
Egoli Gas (Pty) Ltd

As a reticulator, Egoli Gas provides natural gas to homes and businesses via underground pipes.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (23/10/2026)
23rd October 2026 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

➕

➕

➕

➕

➕

RESEARCH CHANNEL AFRICA

SUBSCRIBE

➕

➕

➕

➕

➕

➕

➕

➕

➕

➕

CORPORATE PACKAGES

CLICK FOR A QUOTATION

➕

➕







sq:0.059 0.081s - 135pq - 2rq
Subscribe Now