Etango-8 uranium project, Namibia – update

Photo by Bannerman Energy
Name of the Project
Etango-8 uranium project.
Location
Erongo region, about 30 km east-southeast of Swakopmund, in Namibia.
Project Owner/s
The Etango project is effectively owned by Australian- and Namibian-listed uranium developer Bannerman Energy (52.25%), CNNC Overseas Limited (42.75%) and One Economy Foundation (5%, loan-carried). Bannerman and CNOL hold their interests through the Etango Joint Venture (JV), which owns 95% of the project.
Project Description
A definitive feasibility study was completed in December 2022. This confirmed to a definitive level the strong technical and economic viability of conventional openpit mining and heap-leach processing of the Etango deposit as an eight-million-tonne-a-year throughput operation – for average output of 3.5-million pounds a year of triuranium octoxide (U3O8).
In March 2024, a scoping study showed the capacity to increase production to 6.7-million pounds a year of U3O8.
The Etango-8 base case has an estimated operating life of about 15 years and total production of 52.6-million pounds of U3O8.
Two future-phase development options have been proposed:
- an expansion of mine and plant throughput to 16-million tonnes a year – Etango-XP; and
- a life-of-mine extension with mine and plant throughput maintained at eight-million tonnes a year – Etango-XT.
The final investment decision (FID) covers the Etango-8 base case; the expansion and life-extension options remain separate future development opportunities.
Potential Job Creation
Bannerman reported about 523 contractor personnel on site in its early works update of September 29, 2026. This is a construction workforce count, not a forecast of permanent operating jobs.
Net Present Value/Internal Rate of Return
The previously reported project-level after-tax net present value, at an 8% discount rate, is $390-million, with an internal rate of return of 21.1%, on the updated 2024 cost basis. These are study estimates, not Bannerman’s attributable share or newly calculated FID returns.
Capital Expenditure
The FID announcement forecasts preproduction capital of about $353-million, including about $64-million already incurred through early works to September 30, 2026. The latter figure includes cash held in the Namibian subsidiary.
Planned Start/End Date
A positive FID was announced on October 23, 2026, allowing for full-scale construction. Commissioning and first yellowcake production are expected in 2028.
Latest Developments
The CNOL transaction was completed on September 24, 2026. CNOL paid $294.5-million into the JV and $25.9-million to Bannerman as reimbursement of eligible project expenditure. CNOL is entitled to 60% of life-of-mine output on market-based terms; Bannerman controls the marketing of the remaining 40%.
At September 30, the JV held about $295-million, excluding cash, in the Namibian subsidiary, to fund residual forecast preproduction capital. Bannerman held about A$175-million, excluding JV cash, covering its remaining forecast working capital share through construction and ramp-up into targeted commercial production. Construction is funded on a debt-free basis.
Bulk earthworks are substantively complete and detailed design is well advanced.
Key Contracts, Suppliers and Consultants
Wood plc (study lead – process plant design and related infrastructure, plant capital and operating cost estimates); Qubeka Mining Consultants (geology review, mineral reserve estimate, mine planning and mining cost estimates); Snowden Optiro (mineral resource estimate); Creo Engineering Solutions (engineering support for Bannerman owner’s team); MineTechnics (openpit geotechnical parameters); Lund Consulting Engineers (water supply infrastructure); Addiza Energy Solutions (external electrical supply infrastructure); A.Speiser Environmental Consultants (environmental-impact assessments); Namisun Environmental Projects & Developments (conceptual mine closure plan); AN Construction (pumpstation foundations and pipe bridge over the Swakop river); Tulela Mining & Construction (blasting, crushing and screening of heap leach drainage aggregate); K Neumayer Civil Contractors (Phase 1 and Phase 2A concrete works); Transmission Consulting Services, with Addiza Energy Solutions (EPCM for the 132 kV line and substations); Windhoek Consulting Engineers (Walvis Bay acid storage and handling facility design); NamWater (permanent water supply); and NamPower (permanent electricity supply).
Contact Details for Project Information
Bannerman Energy, tel +61 8 9381 1436 or email info@bmnenergy.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation