https://newsletter-mw.creamermedia.com
Construction|Electrical|Engineering|Gold|Infrastructure|Mining|Motors|PROJECT|Resources|Road|Service|Water|Equipment|Environmental|Infrastructure
Construction|Electrical|Engineering|Gold|Infrastructure|Mining|Motors|PROJECT|Resources|Road|Service|Water|Equipment|Environmental|Infrastructure
construction|electrical|engineering|gold|infrastructure|mining|motors|project|resources|road|service|water|equipment|environmental|infrastructure

Eskay Creek gold/silver project, Canada – update

Ore samples from the Eskay Creek project

Photo by Skeena Resources

10th April 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Eskay Creek gold/silver project.

Location
Tahltan Territory, in the Golden Triangle of north-west British Columbia, Canada.

Project Owner/s
Precious metals developer Skeena Resources.

Project Description
A 2023 definitive feasibility study (DFS) supports a conventional openpit mining and milling operation.

Openpit mining will follow down slope of the ridge where the deposit is located. The north pit will comprise ten phases, while the south pit will be developed as a single phase. 

The project will have a processing life of about 12 years producing 2.8-million ounces of gold, 3.94-million ounces of gold equivalent and 81.14-million ounces of silver over the life-of-mine.

The DFS outlines an average production profile of 455 000 gold equivalent ounces in the first five years of operation. In Years 1 to 5, three-million tonnes a year will be processed. A pebble crusher will be added in Year 3 to maintain production when harder ore is processed in Year 4.

An expansion will be completed in Year 5 to increase processing capacity to 3.5-million tonnes a year when harder and lower-grade ore is processed, starting in Year 6. Only minor upgrades will be required to the processing plant equipment list, as most of the major equipment items, such as the mills, are presized for this higher throughput and harder ore. Mill-motor footprints will be capable of having larger electrical motors installed at that time.

Run-of-mine material will be trucked from the openpits and either stockpiled or directly fed into the primary crusher.

Potential Job Creation
The project will create more than 800 direct jobs and potentially 2 000 jobs for outside service and contract organisations.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a 5% discount rate, of C$3.11-billion and an internal rate of return of 53.1%, with a payback of 1.1 years.

Capital Expenditure
The updated 2026 construction budget estimates total project cost at $659-million, including about $35-million in contingency. As at December 31, 2025, about $354-million remained to be spent to achieve initial production.

Planned Start/End Date
Initial production is targeted for the second quarter of 2027, followed by commercial production in the third quarter of 2027.

Latest Developments
The project is about 49% complete and 66% of project costs have been contractually committed. 

Major completed works include the delivery of initial large mining equipment, access-road bridge replacements, process plant pad earthworks and assay laboratory construction. 

Work under way includes the tailings facility, permanent camp, water treatment facilities, electrical infrastructure, process plant construction and detailed engineering. 

The permitting process was completed in February 2026 with receipt of the Environmental Management Act permit.

Key Contracts, Suppliers and Consultants
Global Resource Engineering and Sedgman Canada (2023 DFS).

Contact Details for Project Information
Skeena Resources, tel +1 604 684 8725 or email info@skeenaresources.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Axiom Hydraulics
Axiom Hydraulics

Axiom Hydraulics is a trusted leader in South Africa’s hydraulic industry, delivering world-class components, systems, and engineering expertise...

VISIT SHOWROOM 
Sulzer Pumps (SA) (Pty) Ltd
Sulzer Pumps (SA) (Pty) Ltd

Sulzer South Africa, established in 1922, partners with critical industries like power, oil & gas, water, mining, and chemicals to boost...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.077 0.211s - 108pq - 2rq
Subscribe Now