Alara lifts Oman copper output above nameplate after ramp-up hurdles
ASX-listed Alara Resources has pushed production above nameplate at its Al Wash-hi Majaza copper operation in Oman, with output running more than 6% ahead of design capacity following months of commissioning challenges.
The milestone marks a turning point for the project, which previously faced tailings filtration issues during ramp-up but has now delivered consistent performance over a rolling six-month period.
On a year-to-date basis, mine production is 6.4% above nameplate, while concentrator output is 6.1% higher, with the operation expected to exceed 40 000 t of copper concentrate for the 2026 financial year.
MD Atmavireshwar Sthapak said reaching and surpassing nameplate capacity was a testament to the dedication, expertise, and collaboration of the entire team.
"This milestone not only demonstrates the strength of our operations, but also reinforces our confidence in the long-term potential of our flagship Al Wash-hi Majaza copper project.”
The company expects to produce more than 40 000 t of copper concentrate in the 2026 financial year.
Meanwhile, Alara confirmed that its thirty-eighth shipment of copper/gold concentrate, comprising about 1 389 t of product, has been delivered to Sohar port, but dispatch has been delayed owing to regional uncertainties.
The company is working with port authorities and shipping partners to confirm a revised departure date.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation