Hombre Muerto West lithium project, Argentina/Bolivia/Chile – update

Hombre Muerto lithium operation

Photo by Galan Lithium

5th June 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Hombre Muerto West (HMW) lithium project.

Location
South American lithium triangle, which spans the borders of Argentina, Bolivia and Chile.

Project Owner/s
ASX-listed Galan Lithium.

Project Description
The HMW project is separated into four production phases. 

The initial Phase 1 definitive feasibility study (DFS) focused on the production of 5 400 t/y of lithium carbonate equivalent (LCE). In September 2024, Galan MD JP Vargas de la Vega indicated that the company had adopted a lower capital intensity Phase 1 development to an initial 4 000 t/y LCE rate in light of market conditions.

The Phase 2 DFS targets 21 000 t/y lithium carbonate equivalent in 2026, followed by Phase 3 production of 40 000 t/y lithium carbonate equivalent by 2028 and the Phase 4 production target of 60 000 t/y lithium carbonate equivalent by 2030. 

Phase 4 will include lithium brine sourced from HMW, and Candelas – Galan’s other 100%-owned project, in Argentina.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Phase 1 delivers an after-tax net present value, at an 8% discount rate, of $460-million and an internal rate of return of 36%, with a payback of two years from the start of construction.

Capital Expenditure
The Phase 1 project is estimated at $104-million, in addition to the $278-million contemplated in the Phase 2 study, with the total Phase 1 and Phase 2 capital cost estimated at $382-million.

Planned Start/End Date
Galan Lithium achieved first processed lithium chloride at HMW in May 2026, marking the end of wet plant commissioning.

Latest Developments
Optimisation is under way.

Galan aims to produce commercial lithium chloride concentrate and start with product sales in the second half of the year.

So far, the company confirms excellent rejection of impurities from its nanofiltration plant, which is consistent with design specifications.

The company’s 10 000 t lithium carbonate equivalent (LCE) brine inventory in evaporation ponds on site provides immediate feedstock for a sustained ramp-up in production.

Galan’s first focus is to stabilise production at HMW’s nameplate capacity of 4 000 t/y of LCE, before ramping up and scaling to 5 200 t/y of LCE.

Pond construction works for the expanded 5 200 t/y LCE Phase 1 will start shortly, with the capacity uplift targeted for the first half of 2027.

Key Contracts, Suppliers and Consultants
Ad-Infinitum (feasibility study work and lithium recovery method); SRK Consulting (mineral resources and reserve estimates); AIA Engineering, Consulting Services International and EIC Engineering (pond designs and water contour channels); M3 Engineering and Technology Corporation (reviewing and documenting the recovery method and the civil material takeoff quantities for ponds and water contour channels, developing the engineering design of the reagents and filtering plant); M3 (project layout, infrastructure designs, capital cost and operating-cost estimates and economic evaluation); and Wood Mackenzie and iLiMarkets (price estimates of the lithium carbonate and lithium chloride concentrate).

Contact Details for Project Information
Galan Lithium, tel +61 8 9322 6283 or email admin@galanlithium.com.au.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 
ACTOM
ACTOM

Your one-stop global energy-solution partner

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (05/06/2026)
5th June 2026 By: Martin Creamer
Photo of Martin Creamer
New cadastre, Sam Molefi, PyroFuZA make headlines
5th June 2026
Magazine round up | 05 June 2026
Magazine round up | 05 June 2026
5th June 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.045 0.175s - 116pq - 2rq
Subscribe Now